7 Steps for Applying Net Metering in New Delhi
by Loom Solar India's premium Solar Brand StoreHere, we will know about how solar net metering process work In Delhi, we have to follow simple 7 steps for net meter file submission.
Step 1- Express
intent to install via Net Metering Application Form
Receiving all required document from the client (ID proof, Residential Proof, latest paid light bill and NOC copy (if any co-owner/landlord), written request application of net meter by client site.
Step 2- After completing all documents, we summit (annexure-1) application form online or offline mode to the discoms.
Step 3- Discom site engineers visit customer site and verify all parameters as per Delhi electricity regulation policy (like existing approval of old meter, shadow area, nearest transformer etc.) and give approval for rooftop solar project by E-mail.
Step 4- After approval, (usually we get in 7 days) vendor/customer will install and commission solar rooftop project as per IPGCL solar policy.
Step 5- After
installation site, we summit annexure-2 (Detailed SLD of solar plant signed by
customer and Solar Plant Installer with stamp)
Example: Certificates of system such as IEC 61727, IEC 62116 for Inverter, IEC 61215, IEC 61730 for PV modules signed by Customer and Solar Plant Installer with stamp Detailed list of components (Wire/structure/connector/shadow area/direction etc.) used in Renewable Energy System signed by Customer and Solar Plant Installer with stamp.
Net Metering Connection Agreement on Rs.100/- non judicial stamp paper, duly attested by Notary public signed by customer on each page with stamp Solar Plant Installation Certificate signed by customer and Solar Plant Installer with stamp, post installation of plant.
Step 6- After submission of the annexure-2 within 6-7 days discom site engineers visit site and verify all solar components and electrical connectivity parameters by CEA regulations and summit test report to discom.
Step 7- After
successfully commission site discom install solar net meter at site(in Delhi,
net meter is provided by discoms only, so you don’t need to buy it from local
market). Net meter cost (usually rs. 8000-10,000) auto debited by client end in
next billing month.