Test Information:

Total Questions: 100

Test Number: C_TPLM22_64

Vendor Name: SAP

Cert Name:  SAP Certified Application Associate

Test Name:  SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4

Official Site: http://www.examsboost.com

For More Details: https://www.examsboost.com/test/c_tplm22_64/


Question: 1

 

How can material components be assigned to network activities?

Note: There are three (3) correct answers to this question.

 

A. By assigning them manually

B. Using the bill of materials transfer 

C. Using assigned sales orders

D. Using ProMan

E. Using the Internet-based catalog

 

Answer: ABE    

 

Question: 2

 

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?

Please choose the correct answer.

 

A. The system status created is active.

B. The system status master data locked is activate.

C. You are not the responsible person for that WBS element.

D. The confirmation exceeds the budget assigned to the WBS.

 

Answer: A    

 

Question: 3

 

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?

Please choose the correct answer.

 

A. Bottom-up

B. Strict bottom-up

C. Free planning

D. Top-down

 

Answer: A    

 

Question: 4

 

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?

Please choose the correct answer.

 

A. Standard time scheduling

B. Standard Bill of Material (BOM)

C. Standard cost planning

D. Standard Milestones

 

Answer: D   

 

Question: 5

 

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?

Note: There are three (3) correct answers to this question.

 

A. Scheduling of subnetworks and subordinate internal orders

B. Introduction of a configurable level concept for the targeted selection of subnetworks

C. Scheduling that takes available capacities and material availability into account 

D. Improve performance through the targeted selection of subnetworks to be scheduled.

E. Detailed subnetwork monitor

 

Answer: BDE    

 

Test Information:

Total Questions: 100

Test Number: C_TPLM22_64

Vendor Name: SAP

Cert Name:  SAP Certified Application Associate

Test Name:  SAP Certified Application Associate - Project System with SAP ERP 6.0 EHP4

Official Site: http://www.examsboost.com

For More Details: https://www.examsboost.com/test/c_tplm22_64/