The WAPC Approval Timeline: How Long Does Subdivision Actually Take?

Posted by Vision Surveys
8
2 days ago
97 Views
Image

You want to split your land up and sell the new lot. The biggest question on your mind is simple. How long will this take? The Western Australian Planning Commission controls the main clock. But many other factors come into play. 

Understanding this timeline helps you plan your cash flow. It helps you manage your expectations. To get this right from day one, you need a reliable subdivision surveyor in Perth to manage the application.

How a Subdivision Surveyor Expert in Perth Speeds Up the Process?

The clock starts ticking the moment you lodge your application. This is where your choice of professional matters. A professional subdivision surveyor in Perth will prepare your initial Form 1A application. 

If your application has errors, the WAPC will pause the assessment. They will ask for more information. This adds weeks to your timeline. An experienced surveyor will get it right the first time. They know exactly what the WAPC needs to see. This keeps your application moving through the system without unnecessary stops.

The First 90 Days: Conditional Approval Period

Once your surveyor submits the application, the WAPC has a statutory timeframe to make a decision. This period is 90 days. It is rare for them to finish much earlier than this. During these three months, they do not just sit on your file. They send your plans to other agencies.

Western Power, the Water Corporation, and your local council all get a say. They tell the WAPC if your new lots can connect to their services. You get to check if your driveway is safe. And if everyone agrees, the WAPC issues a letter of Conditional Approval. This does not mean you have the new titles yet. It means you have permission to start the physical work.

The Works Phase: Where You Control the Speed

This next stage depends on you and your trades. The Conditional Approval letter lists requirements you must meet. You might need to demolish an old shed. You will likely need to install a new sewer junction. 

In a busy market, finding a drainer or an electrician takes time. Budget for at least three to four months here. Delays with Western Power installation are common. You cannot move to the next step until every condition on that list is complete. Your subdivision surveyor in Perth can often recommend reliable trades to keep things moving.

The Final Stretch: Clearances and Titles

You finish the site works. Now you must prove it. Your surveyor goes back to the agencies. They ask for clearance. This confirms you met every condition. 

Once you have all the clearance letters, your surveyor sends the final plan to the WAPC for endorsement. After the WAPC stamps the plan, it goes to Landgate. This is the final office. They register the new titles. This last administrative shuffling takes about six to eight weeks.

Summary of the Timeline by Subdivision Surveyor in Perth

So, what is the total time?

Application Assessment: 3 months

Civil Works: 3 to 4 months (variable)

Clearances and Titles: 2 months

A standard backyard subdivision takes about eight to nine months. If you encounter complex sewer issues or slow trades, it often stretches to a year.

On a concluding note, subdivision is not a quick cash grab. It is a process with strict legal steps. You cannot rush the government agencies, but you can prepare well. Hire the right subdivision surveyor in Perth to avoid mistakes. Get started with a solid plan and your timeline follow accordingly.