How Long will a Subdivision Surveyor Take in Perth?
If you are planning to divide your property into smaller lots, one of the first questions you will likely ask is how long the process will take. Subdivision can be exciting as it will add value to your land. However, it comes with some necessary steps that only a licensed surveyor can take care of. If you are hiring a subdivision surveyor in Perth then you must know the timeline involved. From the initial consultation to final approvals, the time frame can vary based on a variety of factors.
Getting to Know About Your Subdivision Timeline
The duration of a subdivision project is not the same for every property. Factors such as zoning, size of the block, number of lots, and existing infrastructure can all affect how long it takes.
On average, a straightforward subdivision through your surveyor in Perth can take anywhere from 6 to 12 months. More complex projects will take much longer time calling for additional approvals.
Some of the key stages include:
- Initial consultation and feasibility study
- Surveying and site assessment
- Lodgement of subdivision application to Western Australian Planning Commission
- Referral to local council and service authorities
- Clearance of conditions
- Final survey and plan lodgement
- Title issuance by Landgate
What Can Affect the Timeframe for Subdivision Surveyor in Perth?
- Approval from Local Council: Each council has its own assessment timelines. Some may process within weeks while others can take months.
- Service Authorities: Water, electricity, and sewerage connections need to be checked and approved, which can delay progress.
- Site Complexities: Sloping land, easements, or environmental considerations often require more detailed planning through subdivision surveyor in Perth.
- Number of Lots: A simple two-lot subdivision is faster than larger developments.
According to the Western Australian Planning Commission, the statutory time frame for subdivision approval is 90 days, but real-world cases often take longer due to conditions and compliance steps.
How a Subdivision Surveyor in Perth Can Help You?
Working with an experienced Subdivision surveyor in Perth can make a big difference in how quickly the process will run. A professional surveyor can:
- Provide an accurate feasibility study before you commit
- Prepare and lodge all applications correctly
- Liaise with local councils and service authorities
- Carry out the required surveys with precision
- Ensure compliance with all subdivision conditions
Having Realistic Expectations as Property Owners
It is important to approach subdivision with realistic expectations. While many people hope for quick results, even a simple project can involve multiple stakeholders and formal steps that cannot be rushed.
For instance:
- Feasibility and Survey: 2 to 4 weeks
- WAPC Application and Approval: 3 to 4 months
- Service Authority Clearances: 2 to 3 months
- Final Survey and Lodgement: 4 to 6 weeks
- Title Issuance: 4 to 8 weeks
Subdivision is a valuable way to bring potential in your property, but it does take time. Knowing the stages and possible challenges will help you set the right expectations. With the right support from subdivision surveyors in Perth, you can your subdivision journey will be handled professionally.